Similar rules apply to the relocation of production lines as to the setting up of production lines; however, further requirements including those of logistics have to be met. The same quality and accuracy to detail of documents (drawings, circuit diagrams, specifications, etc.) is required as for setting up a production line in a new building.
For successfully moving a production line, on-schedule and on-budget, twelve steps have to be carried out:
Stages of relocating a factory/production line:
• Planning
• Preparations for disassembly
• Disassembly
• Cleaning/Disposal
• Packaging
• Transport
• Preparations for installation
• Installation
• Final cleaning
• Start-up
• Start of production/Breaking in of machines
Preparations for disassembly
• Insurance policies, liability
• Select disassembly team members (electrical, mechanical)
• Tools, lifting tools, forklifts, cranes
• Intermediate storage facilities, cleaning facilities
• Work permits (nights, weekends)
Disassembly, cleaning and disposal
• Labeling of system components
• Comparison/Review of foundation dimensions with foundation plans
• De-energize the system (power, oil, etc.)
• Draining of supply lines
• Disconnection of electrical cables
• Electrical/Electronic disassembly
• Disassembly of measurement technology
• Backing up controller programs
• Disassembly and cleaning of mechanical components
• Disposal of residual substances
Disassembly work represents the simplest part of relocation measures; however, the quality of disassembly work determines whether installation procedures will be carried out on-schedule and whether the system will work correctly after installation.
Steps for start-up/inspections/training
• System start-up with production material
• Optimization of control systems
• Start-up / Run down test / Safety criteria test
• System optimization, depending on recipes
• Acceptance test
Achievement of these objectives is guaranteed by the provision of comprehensive services during all relocation stages.